Begin March aerial photos: Facing west, foundation for new sound barrier wall along WB 25A on-ramp

Facing southwest, foundation for new sound barrier wall along WB 25A on-ramp

Facing west, the Project limits beginning from Pierpont Road vicinity

Facing west, WB 25 off-ramp and EB 25 on-ramp at Scott Road Bridge

Facing north, former WB 25 off-ramp with new sewer construction, and new WB 25 off-ramp

Facing south, Scott Road Bridge vicinity with realigned Mad River

Facing south, Scott Road Bridge vicinity with realigned Mad River, new off-ramp and Plank Road alignment

Facing southeast, new center pier footing and abutment under construction for Scott Road Bridge

Facing east, Scott Road Bridge with western center pier footing and abutments under construction

Facing north, Scott Road Bridge new eastern portion, and western portion under construction

Facing west, I-84 roadway and new median west of Scott Road Bridge

Facing northeast, new culvert for Mad River under I-84 at WB 25 on-ramp, west of Scott Road Bridge

Facing southwest, I-84 roadway and median construction, and path for future Plank Road East

Facing west, I-84 and median reconstruction, and new path for Plank Road East, between two new retaining walls

Facing north, path for new Plank Road East under construction between two retaining walls, north of I-84

Facing west, east of Harpers Ferry Road is new culvert for Mad River under I-84

Facing south, Harpers Ferry Road Bridge vicinity

Facing west, Harpers Ferry Road vicinity with new WB 25 on-ramp construction

Facing south, new Reidville Drive and EB I-84 alignment, east of Harpers Ferry Road

Facing southeast, new Reidville Drive and EB I-84 in their new alignments

Facing south, new EB 25 off-ramp over the Mad River

Facing southeast, pumping concrete into footing for new WB on-ramp bridge over Mad River

Facing northwest, Harpers Ferry Road Bridge with future WB I-84 adjacent to new EB I-84 alignment

Facing northwest, pumping concrete into footing of new WB 25 on-ramp, west of Harpers Ferry Road Bridge

Facing northwest, towards Hamilton Avenue; lower right is new I-84 and EB 25 off-ramp bridge over Mad River

Facing south, new I-84 and EB 25 off-ramp bridge over the Mad River, western crossing

Facing northeast, new I-84, EB 25 off-ramp and pedestrian bridges over the Mad River, western crossing

Facing north, new I-84, EB 25 off-ramp and pedestrian bridges over the Mad River, western crossing; and sound barrier wall

Facing northwest, Hamilton Avenue Bridge vicinity

Facing west, eastern portion of Hamilton Avenue Bridge with stay-in-place forms on bridge deck

Facing southwest, future EB 23 on-ramp and eastern portion of Hamilton Avenue Bridge under construction

Facing east, Hamilton Avenue Bridge

Facing northeast, Hamilton Avenue Bridge

Facing northeast, Hamilton Avenue Bridge eastern portion, EB 23 off-ramp and future EB on-ramp intersection

Facing southeast, I-84 west of Hamilton Avenue, with roadway and median work to end of Project limits at Washington Street

End March aerial photos: Facing east, from Hamilton Avenue, and beyond; the I-84 Waterbury Project

Sequence of 7 photos depicting construction of foundation of sound barrier wall along WB I-84, west of WB 25 off-ramp

Drilling holes for foundation of sound barrier wall along WB I-84, west of WB 25 off-ramp

Rebar cages await installation in drilled foundation of sound barrier wall east of WB 25 off-ramp

Rebar cage in place in form for foundation of sound barrier wall, under construction

Form for foundation of new sound barrier wall

Anchor bolt form is lifted for installation in rebar cage form for sound barrier wall

Foundation for sound barrier wall with concrete poured and anchor bolts in place

Median work west of Scott Road Bridge

Construction of leveling pad for new I-84 median (view from path of future Plank Road East)

Installation of precast concrete median sections on leveling pad

Conduit installed in median

Median work and installation of foundations for illuminations

Placing subgrade material for future WB I-84, west of Scott Road Bridge

Drainage installation along northwest side of future Scott Road

Drilling holes for explosives before blasting along former WB 25 off-ramp.

Drilling holes for explosives before blasting along former WB 25 off-ramp

Blast mats cover explosives before blasting

Workers install seeded topsoil to restore the slope behind new retaining wall on north side of futrue Plank Road East

Workers install seeded topsoil for slope protection behind retaining wall along future Plank Road East

Drainage at the top of retaining wall

Completed slope behind retaining wall, west of WB 25 on-ramp

Begin February aerial photos: Facing west, the eastern Project limits from Pierpont Road

Facing southwest, I-84 west of Pierpont Road

Facing west, I-84 and Scott Road Bridge

Facing southwest, I-84 with new on- and off-ramps and Scott Road Bridge

Facing south, Scott Road Bridge with new eastern portion, and western portion being dismantled

Facing southeast, new sanitary sewer/pipework along the former WB 25 off-ramp

Facing northeast, new sanitary sewer/pipework along the former WB 25 off-ramp

With north at top, Scott Road Bridge with steel girdges for removal on western portion

With east at top, Scott Road Bridge before removal of structural steel on western portion

Facing south, WB 25 on-ramp west of Scott Road Bridge, with I-84 median work

Facing southeast, WB 25 on-ramp west of Scott Road Bridge, with I-84 median work

Facing east, west of Scott Road Bridge, I-84 median work, and retaining walls adjacent to future Plank Road East (lower left)

Facing north, west of Scott Road Bridge, retaining walls adjacent to WB I-84 and future Plank Road East (lower left)

Facing northwest, New EB I-84 with median work underway

Facing north, new culvert under, and new retaining wall adjacent to, new EB I-84

Facing west, Harpers Ferry Road Bridge vicinity

Facing south, Harpers Ferry Road Bridge with EB I-84 in its new alignment

Facing southeast, Harpers Ferry Road and Plank Road with Mad River

Facing southeast, Harpers Ferry Road Bridge with demolition of former EB I-84 and EB 25 off-ramp

Facing southeast, EB I-84 in new alignment, and construction of future WB I-84 bridge adjacent to it

Facing east, Harpers Ferry Road Bridge vicinity

Facing west, the new EB 25 off-ramp and new Reidville Drive intersection on Harpers Ferry Road

With northwest at top, Harpers Ferry Road Bridge

Demolition of former EB I-84 and EB 25 off-ramp, and construction of footing for new WB 25 on-ramp bridge

Facing east, I-84 east of Harpers Ferry Road

With east at top, Reidville Drive from Harpers Ferry Road

With north at top, new EB 25 off-ramp and bridge over Mad River

Facing south, east of Harpers Ferry Road, demolition of former EB I-84

With Hamilton Park at north on right, new I-84 bridge over Mad River western crossing, and future EB 25 off-ramp

Facing northeast, new I-84 bridge over Mad River western crossing, and future EB 25 off-ramp; new pedestrian bridge (right)

Facing northwest, I-84 east of Hamilton Avenue Bridge, with future EB 23 on-ramp, top left

Facing west, Hamilton Avenue Bridge

Facing west, Hamilton Avenue Bridge with new structural steel on eastern portion

Facing southwest, future EB 23 on-ramp, from Hamilton Avenue Bridge

Facing south, future EB 23 on-ramp/bridge, from Hamilton Avenue Bridge

Facing southeast, Hamilton Avenue Bridge with new western portion, and new structural steel on eastern portion

Facing north, Hamilton Avenue Bridge with new EB 25 off-ramp beneath it

Facing west, the Project west of Hamilton Avenue to end of Project limits, at Washington Street

End February aerial shots: Facing east, the Project from west of Hamilton Avenue

Facing north, workers backfill, grade and restore the slope behind the new retaining wall, west of WB 25 on-ramp

Facing north, workers backfill, grade and restore the slope behind the new retaining wall, west of WB 25 on-ramp

Facing west, worker prepares the footing for placement of the new I-84 median barrier

Facing west, workers assist in placement of the new I-84 median barrier

Begin January 2018 aerial views: from eastern project limits at Pierpont Road looking westward

Facing southwest, I-84 over Pierpont Road with new lanes, median, retaining walls and sound barrier wall

Facing west, toward Scott Road Bridge vicinity

Facing west, toward Scott Road Bridge with new eastern portion, and western portion under demolition

Facing south, Scott Road Bridge with new eastern portion, and western portion under demolition

With east at top, Scott Road Bridge with new eastern portion, and western portion under demolition

Facing north, new Plank Road East and WB 25 off-ramp, north of Scott Road Bridge and WB I-84

Facing north, WB 25 off ramp and sound barrier wall, with demolition of old ramp, north of Beaver Pond Brook

Facing northwest, WB 25 off ramp with demolition of old ramp, north of rerouted Beaver Pond Brook

Facing west, I-84 and WB 25 on-ramp, west of Scott Road Bridge

Facing west, I-84 and WB 25 on-ramp, west of Scott Road Bridge

Facing east, I-84 and WB 25 on-ramp, west of Scott Road Bridge; median and lane work

Facing north, new retaining walls and future path of Plank Road East, between Scott and Harpers Ferry Roads

Facing northwest, new retaining walls and future path of Plank Road East, between Scott and Harpers Ferry Roads

Facing west, I-84 with WB 25 on-ramp and retaining walls to the north

Facing west, I-84 retaining walls to the north for future Plank Road East to Harpers Ferry Road vicinity

Facing south, New Reidville Drive, Harpers Ferry Road Bridge and EB I-84 in its new alignment; foreground: existing WB I-84 and former EB I-84

Facing south, Harpers Ferry Road Bridge, with demolition of former EB 25 off-ramp (lower right above WB I-84)

Facing south, new Reidville Drive, with path of former Reidville Drive (with dump truck) north of EB I-84

Facing east; new culvert under new EB I-84 and future WB I-84; demolished former EB I-84 and existing WB I-84

Facing north toward Plank Road/Harpers Ferry Road vicinity

Facing south, new Harpers Ferry Road Bridge with new EB I-84 alignment and EB 25 off-ramp and Reidville Drive to the north

Facing southwest, Harpers Ferry Road vicinity with new Plank Road culvert and Mad River

Facing southeast, demolition of former EB 25 off-ramp in preparation for construction of new WB 25 on-ramp

Facing northwest, preparation for pile driving for new WB 25 on-ramp bridge (lower left) from Harpers Ferry Road

Facing west, Harpers Ferry Road vicinty

Facing north, Harpers Ferry Road vicinity with Reidville Drive in foreground

Harpers Ferry Road Bridge with east at top of photo

Facing south, new EB 25 off-ramp over the Mad River

Future WB I-84 bridge over the Mad River, adjacent to new EB I-84, west of Harpers Ferry Road Bridge

Facing east, view of Harpers Ferry Road Bridge vicinity

Facing north, new EB 25 off-ramp and Reidville Drive/Harpers Ferry Road intersection

Facing south, new I-84 bridge over the Mad River eastern crossing, south of Hamilton Park.

Facing west, new I-84 bridge and EB 25 off-ramp bridge over the Mad River western crossing, with Hamilton Park (right)

Facing west, Hamilton Avenue Bridge with steel erection underway on eastern portion over WB I-84

Facing south, Hamilton Avenue Bridge with portion of structural steel in place; girders on bridge and awaiting installation

Facing south, future EB 23 on-ramp from Hamilton Avenue under construction

Facing south, future EB 23 on-ramp from Hamilton Avenue under construction, with EB 25 off-ramp underneath

Steel girders in place on Hamilton Avenue Bridge over WB I-84

Facing east, steel girders in place on Hamilton Avenue Bridge over WB I-84

Facing northeast, future EB 23 on-ramp bridge over EB 25 off-ramp, from Hamilton Avenue

Facing northwest, Hamilton Avenue Bridge vicinity

Facing east, loop ramp from Hamilton Avenue onto I-84, and entry to EB 25 off-ramp

Facing east, view of the project limits from Washington Street vicinity eastward; end Jan. aerial photos

Installation of cross beams during nightime steel erection on Hamilton Avenue Brdge

Installation of girders during nighttime steel erection on Hamilton Avenue Brdge

Crane lifts steel girder during nighttime steel erection on Hamilton Avenue Bridge over EB I-84

Nighttime steel erection on Hamilton Avenue Bridge over westbound I-84

Nighttime steel erection on Hamilton Avenue Bridge over westbound I-84

Nighttime steel erection on Hamilton Avenue Bridge over westbound I-84

Facing west, preparation for removal of former EB Exit 25 off-ramp pavement, west of Harpers Ferry Road Bridge.