Construction Weekly Project Update 8/13/2018

Please see our Interactive Map of the Project limits, with the locations of the construction sites below.
This map is also accessible from our homepage.

Bridges

Bridge 4321 (Hamilton Avenue Bridge)

Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)

Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)

Local Roads

Harpers Ferry Road

Future Plank Road East

I-84 Mainline

I-84 EB (between median and barrier east of Scott Road Bridge, adjacent to EB 25 on-ramp)

Miscellaneous work

Night Work

One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Friday nights

Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)

Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.