Construction Weekly Project Update 8/13/2018
- Bridges
- Local Roads
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Please see our Interactive Map of the Project limits, with the locations of the construction sites below.
This map is also accessible from our homepage.
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Shift to permanent alignment
Bridge 6590 (Future EB 23 on-ramp, east of Hamilton Avenue Bridge)
- Open EB 23 on-ramp
- Open final alignment of EB 25 off-ramp
- Demolish temporary loop ramp
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Drive piles for temporary support tower for steel erection
- Prepare for structural steel delivery
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)
- Structural steel erection and bolt up on western portion on the bridge
Local Roads
Harpers Ferry Road
Future Plank Road East
- Install sound barrier wall
I-84 Mainline
I-84 EB (between median and barrier east of Scott Road Bridge, adjacent to EB 25 on-ramp)
- Excavate subbase on EB I-84
Miscellaneous work
- Open EB 23 on-ramp, final alignment of EB 25 off-ramp, and Hamilton Avenue Bridge to full-width
- Barrier moves (night)
- Pave/guardrail/signs and sidewalk
Night Work
One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Friday nights
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.