Construction Weekly Project Update 7/23/2018
- Bridges
- Culverts
- Local Roads
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Please see our Interactive Map of the Project limits, with the locations of the construction sites below.
This map is also accessible from our homepage.
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
Bridge 1226 (Harpers Ferry Road Bridge)
- Continue demolition of former Harpers Ferry Road Bridge over former I-84
- Continue to demolish former EB 25 off-ramp bridge deck
- Begin demolition of structural steel from EB 25 off-ramp bridge
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Install reinforced concrete wall
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)
- Form and pour abutments 1 and 2 stems and wing walls
- Backfill abutments
- Accept delivery of girders for Stage 2 steel erection (western portion of bridge)
Culverts
Culvert 3727 (Beaver Pond Brook under Harpers Ferry Road, north of I-84)
- Install waterproof membrane
- Install sewer bypass and tie-in near culvert
Local Roads
Harpers Ferry Road
Future Plank Road East
- Install sound barrier wall foundation
Scott Road (and WB 25 off-ramp)
- Continue to excavate Beaver Pond Brook at site of former culvert
I-84 Mainline
I-84 WB (along WB 25A on-ramp, and westward)
- Install posts and panels for sound barrier wall
Miscellaneous work project-wide
- Install camera foundations
- Install permanent signalization at Hamilton Avenue and Scott Road
Night Work
One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Friday nights
- Miscellaneous barrier moves
- Backfill abutments at Scott Road Bridge
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.