Construction Weekly Project Update 7/16/2018
- Bridges
- Culverts
- Retaining Walls
- Local Roads
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Please see our Interactive Map of the Project limits, with the locations of the construction sites below.
This map is also accessible from our homepage.
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Roadway work at approaches to Hamilton Avenue Bridge
- Pave eastern portion of bridge deck (night work)
- Shift traffic onto eastern bridge deck (night work)
Bridge 6590 (Future EB 23 on-ramp, east of Hamilton Avenue Bridge)
- Pave bridge deck and ramp
Bridge 1226 (Harpers Ferry Road Bridge)
- Continue demolition of former Harpers Ferry Road Bridge over former I-84
- Continue to demolish existing EB 25 off-ramp bridge deck
- Begin demolition of structural steel from EB 25 off-ramp bridge
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Form and pour stems and wingwall abutment 2, and backfill
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)
- Form and pour abutments 1 and 2 stems and wing walls
- Backfill abutments
- Accept delivery of girders for Stage 2 steel erection (western portion of bridge)
Culverts
Culvert 3727 (Beaver Pond Brook under Harpers Ferry Road, north of I-84)
- Prep water handling, excavate, and fill with granular material
Retaining Walls
Retaining Wall 109 (East of WB 25 off-ramp)
Retaining Wall 119 (Along south side of future Plank Road East, adjacent to WB I-84)
- Pave Plank Road East between interim 25 off-ramp and culvert 1227 – under I-84, east of Harpers Ferry Road)
Retaining Walls 102 and 103 (On both sides of future EB 23 on-ramp)
Local Roads
Harpers Ferry Road
Future Plank Road East
- Install sound barrier wall foundation
I-84 Mainline
I-84 WB (along WB 25A on-ramp, and westward)
- Install posts and panels for sound barrier wall
Miscellaneous work project-wide
- Install camera foundations
- Install permanent signalization at Hamilton Avenue and Scott Road
Night Work
One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Friday nights
- Paving Hamilton Avenue Bridge and EB 23 on-ramp
- Shift traffic onto eastern portion of Hamilton Avenue Bridge
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.