Construction Weekly Project Update 6/20/2016

Bridges

Bridge 4321 (Hamilton Avenue over I-84)

Bridge 1224 (I-84 over Mad River, western crossing)

Bridge 5774 (Future I-84 over Mad River eastern crossing)

Bridge 6284 (future EB 25 off ramp over Mad River)

Bridge 1226 (Harpers Ferry Road over I-84)

Retaining Walls

Retaining Wall 101 (along I-84 east, of WB Exit 23 off ramp)

Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)

Retaining Wall 110 (along I-84, east of EB 25 on ramp)

Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)

I-84 EB & WB

I-84 WB (west of Scott Road parallel to Plank Road)

I-84 EB off ramp (EB Exit 23 Hamilton Ave)

I-84 WB (from Pierpont Road to WB 25 off ramp)

Local Roads

Reidville Drive

Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)

Sewer Work

Jacking Pit (under I-84 adjacent to former WB 24 off ramp)

I-84 Exit WB 25 off ramp (Beaver Pond Brook/Scott Road)

Rock Blasting

Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)

Night Work on Hamilton Avenue Bridge – Detour Information

I-84 will close and be detoured at Exit 23 between the hours of 11:00 PM to 5:00 AM for night time steel erection on the Hamilton Avenue Bridge, on Sunday June 19 through Thursday June 23, 2016.

Nighttime closures will occur Sunday through Thursday nights as follows:

Detour routes from I-84 EB and WB Exit 23 off ramps are as follows:

Motorists will be guided through the detour route by construction signage, State, and local Police.

The closure of I-84 is to ensure safety of the traveling public during construction.

Hamilton Avenue Bridge Deour for Steel Erection