Construction Weekly Project Update 6/06/2016
- Bridges
- Retaining Walls
- I-84 EB & WB
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Begin steel delivery and prep
- Form and pour pedestals for pier and abutment
Bridge 1224 (I-84 over Mad River, western crossing)
- Set stay in place forms and install fascia brackets
Pedestrian Bridge (over Mad River south of Bridge 1224)
Bridge 5774 (Future I-84 over Mad River eastern crossing)
- Drive production piles abutment 2
- Drive cofferdam abutment 2 and excavate
- Drive test pile abutment 2
- Rebar, form and pour backwalls abutment 1
Bridge 1226 (Harpers Ferry Road over I-84)
- Form and pour abutment 1 footing
Bridge 6284 (future EB 25 off ramp over Mad River)
- Form and pour abutment 1 backwalls
- Strip and backfill abutment 2 footing
- Form and pour stemwalls abutment 2
Retaining Walls
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Excavate
- Form and pour leveling pad
Retaining Wall 110 (along I-84, east of EB 25 on ramp)
- Set parapet/place moment slab
Retaining Wall 113 and 114 (along both sides of future EB 25 off ramp)
I-84 EB & WB
I-84 WB (from Pierpont Road to WB 25 off ramp)
- Place processed aggregate
- Fine grade for asphalt
I-84 WB (east of Scott Road between Retaining Walls 109 and 111)
- Form and place barrier wall
I-84 WB (west of Scott Road parallel to Plank Road)
I-84 EB (west of Scott Road parallel to Reidville Drive)
I-84 EB 23 off ramp (along east side of Hamilton Avenue exit)
- Prep work for noise barrier wall
Sewer Work
South of EB 23 on ramp (Retaining Wall 104)
- Install drainage in front of wall
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Excavate and place new sanitary sewer pipe
Bridge 1224 (I-84 over Mad River, western crossing)
- Install drainage east side of bridge
Local Roads
Reidville Drive
- Install support of excavation
- Excavate for Culvert 003 (just east of the rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Restripe for stage construction
- Excavate and install water and sewer under culvert
Plank Road
Rock Blasting
- Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday and Thursday between 9:30AM and 11:30AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00AM – 3:00PM.
- Traffic stoppages on Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB