Construction Weekly Project Update 5/16/2016
- Bridges
- Retaining Walls
- I-84 EB and WB
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour pedestals for pier and abutment
Bridge 1224 (I-84 over Mad River, western crossing)
- Backfill abutment 1 to backwall
- Continue setting structural steel and bolting at diaphragms and field splices
Bridge 5774 (Future I-84 over Mad River eastern crossing)
- Drive cofferdam abutment 2 and excavate
- Rebar, form and pour backwalls abutment 1
Bridge 6284 (Future EB Exit 25 off ramp over Mad River)
- Form and pour backwalls abutment 1 and footing abutment 2
Retaining Walls
Retaining Wall 101 (along I-84, east of WB Exit 23 off ramp)
- Continue to set blocks and backfill
Retaining Wall 104 (south of EB 23 on ramp)
- Set remaining blocks and parapet
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Excavate and install Temporary Earth Retaining System (TERS)
Retaining Wall 110 (along I-84, east of EB 25 on ramp)
Retaining Wall 111 (along I-84 WB, west of Pierpont Rd.)
- Form and pour moment slab
I-84 EB and WB
I-84 WB
- Form and pour barrier wall east of Scott Road between Retaining Walls 109 and 111
Median reconstruction WB Hamilton Avenue to Washington Street
- Roadway excavation
- Drainage
- Place subbase aggregate
I-84 EB (WB 25 on ramp entry to Scott Road)
Sewer Work
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Excavate and place new sanitary sewer pipe
Local Roads
Reidville Drive
- Sewer and water main work for Culvert 003 (just east of rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
- Utility work
Scott Road (Culvert 014 at Scott Road south of WB 25 off ramp)
- Excavate and install TERS
- Plank Road
- Gas main work
Plank Road East
Rock Blasting
- Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday and Thursday between 9:30AM and 11:30AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00AM – 3:00PM.
- Traffic stoppages on Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB