Construction Weekly Project Update 5/09/2016
- Bridges
- Retaining Walls
- I-84 EB and WB
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour pedestals for pier and abutment
Bridge 1224 (I-84 over Mad River, western crossing)
- Partial demolition of center pier
- Continue setting structural steel
Bridge 5774 (Future I-84 over Mad River eastern crossing)
- Drive cofferdam abutment 1
Bridge 6284 (Future EB Exit 25 off ramp over Mad River)
Bridge 1226 (Harpers Ferry Road over Future I-84)
- Excavate and place granular fill for footing
Retaining Walls
Retaining Wall 101 (along I-84, east of WB Exit 23 off ramp)
Retaining Wall 105 (along Harpers Ferry Road)
- Form and pour remaining moment slab
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Excavate and install temporary earth retaining system
Retaining Wall 110 (along I-84, east of EB 25 on ramp)
Retaining Wall 111 (along I-84 WB, west of Pierpont Rd.)
- Continue placing precast parapet sections
- Form and pour moment slab
I-84 EB and WB
I-84 WB
- Form and pour barrier east of Scott Road between Retaining Walls 109 and 111
Median reconstruction WB Hamilton Avenue to Washington Street
I-84 EB (WB 25 on ramp entry to Scott Road)
Sewer Work
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Excavate and place new sanitary sewer pipe
Local Roads
Reidville Drive
- Sewer and water main work for culvert 003 (just east of rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
- Utility work
Plank Road East (just west of Scott Road; box culvert 06622)
- Backfill and waterproof
- Install leveling pad
Plank Road East
Rock Blasting
- Rock blasting to occur along Reidville Drive. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday and Thursday between 9:30AM and 11:30AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00AM – 3:00PM.
- Traffic stoppages on Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB