- Bridges
- Retaining Walls
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 1224 (I-84 over Mad River, western crossing)
- Pour backwalls and pedestals for abutments 1 and 2
- Partial demolition of center pier
Bridge 6284 (Future EB Exit 25 off ramp over Mad River)
Bridge 1226 (Harpers Ferry Road over Future I-84)
- Excavate and install temporary earth retaining system for abutment 1
Retaining Walls
Retaining Wall 101 (along I-84, east of WB Exit 23 off ramp)
Retaining Wall 109 (along I-84, east of WB Exit 25 off ramp)
- Excavate and install temporary earth retaining system
Retaining Wall 110 (along I-84, east of EB 25 on ramp)
Retaining Wall 113/114 (along both sides of future EB Exit 25 off ramp)
Sewer Work
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Excavate and place new sanitary sewer pipe
Local Roads
Reidville Drive
- Sewer and gas work for culvert 003 (just east of rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
- Utility work
Plank Road East (just west of Scott Road; box culvert 06622)
Rock Blasting
- Rock blasting to occur along Reidville Drive and WB 25 off-ramp Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB