Construction Weekly Project Update 4/11/2016
- Bridges
- Retaining Walls
- I-84 Westbound
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour center pier stem
- Install rebar pier 2 stemwalls
Bridge 1224 (I-84 over Mad River, western crossing)
- Form and pour stemwalls for abutments 1 and 2
- Install rebar
Bridge 05774 (Future I-84 WB over Mad River)
- Drive cofferdam abutment 1
Bridge 06284 (Future EB Exit 25 off ramp over Mad River)
Retaining Walls
Retaining Wall 101 (along I-84 east of WB Exit 23 off ramp)
- Install leveling pads and set blocks
Retaining Wall 104 (south of EB 23 on ramp)
Retaining Wall 110 (along I-84 EB, east of EB 25 on ramp)
Retaining Wall 113/114 (along both sides of future EB Exit 25 off ramp)
I-84 Westbound (east of Scott Road)
- Install foundation single face barrier between retaining walls 109 and 111
Sewer Work
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Drilling and blasting for sewer
- Excavate and place new sanitary sewer pipe
Local Roads
Reidville Drive
- Water work for culvert 003 (just east of rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
- Utility work
Plank Road East (just west of Scott Road)
- Excavate for box culvert 06622 and install support
- Excavate, and form and pour cut off walls
Rock Blasting
- Rock blasting to occur along Reidville Drive and WB 25 off-ramp Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB