Construction Weekly Project Update 3/28/2016
- Bridges
- Retaining Walls
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour abutment 1 wing wall stem
- Install rebar pier 2 stemwall
Bridge 1224 (I-84 over Mad River, western crossing)
- Install rebar, form and pour stemwalls abutment 2 and abutment 1 stemwalls
Bridge 6284 (Future EB Exit 25 off ramp over Mad River)
- Establish cofferdam for abutment 2 site
- Pile driving for abutment 2
Retaining Walls
Retaining Wall 101 (along I-84 east of WB Exit 23 off ramp)
- Establish haul road
- Form and pour sign foundation
Retaining Wall 104 (south of EB 23 on ramp)
- Continue to place and backfill concrete block sections
Retaining Wall 110 (along I-84 EB, east of EB 25 on ramp)
- Backfill and grade entire wall
Retaining Wall 113/114 (along both sides of future EB Exit 25 off ramp)
- Form and pour leveling pad
- Install precast concrete panels and backfill
Sewer Work
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Drilling and blasting for sewer
- Excavate and place new sanitary sewer pipe
Local Roads
Reidville Drive
- Water work for culvert 003 (just east of rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
- Utility work
Plank Road East (just west of Scott Road)
- Excavate for box culvert 06622 and install support
- Excavate, and form and pour cut off walls
Rock Blasting
- Rock blasting to occur along Reidville Drive Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Reuse Stockpile Area (RSA)
- Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
- Trucking excavated material to RSA at Exit 30 WB