Construction Weekly Project Update 2/29/2016
- Bridges
- Retaining Walls
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour abutment 1 wing wall stem
- Install rebar abutment 1 wing wall step footing
- Install rebar pier 2 stemwall
Bridge 1224 (I-84 over Mad River, western crossing)
- Construction of cofferdam and pile driving for abutment 1
- Install rebar at stemwalls abutment 2
- Form and pour stemwalls abutment 2
Bridge 5774 (Future I-84 over Mad River, eastern crossing)
- Install rebar, form and pour abutment 1 wingwall sections
Bridge 6284 (Future EB Exit 25 off ramp over Mad River)
- Prep/establish crane pad for abutment 2 site
Retaining Walls
Retaining Wall 101 (along I-84 east of WB Exit 23 off ramp)
- Excavate for temporary earth retaining system
Retaining Wall 104 (south of EB 23 on ramp)
- Form, rig, and pour leveling pad
- Continue to place and backfill concrete block sections
- Install temporary earth retaining system
Retaining Wall 110 (along I-84 EB, east of EB 25 on ramp)
- Place reinforced concrete sections and backfill
Retaining Wall 111 (along I-84, WB west of Pierpont Road)
- Form, rig, and pour leveling pad
- Continue to place concrete blocks and backfill
Retaining Wall 113/114 (along both sides of future EB Exit 25 off ramp)
- Excavate for leveling pad
Sewer Work
Jacking Pit (under I-84 adjacent to old WB 24 off ramp)
Retaining Wall 104 (south of EB 23 on ramp)
- Install sewer behind Retaining Wall 104
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Excavate and place new sanitary sewer pipe
Local Roads
Reidville Drive
- Water work for culvert 003, (just east of rock cut)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Plank Road East (just west of Scott Road)
- Excavate for box culvert 06622
- Utilities work
Rock Blasting
- Rock blasting to occur along Reidville Drive Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).