Construction Weekly Project Update 2/15/2016
- Bridges
- Retaining Walls
- Sewer Work
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install rebar abutment 1 wingwall step footing
- Form and pour pier 2
Bridge 1224 (I-84 over Mad River, western crossing)
- Form and pour abutment 2 footing
- Construction of cofferdam and pile driving for abutment 1
- Rebar stemwalls abutment 2
Bridge 5774 (Future I-84 over Mad River, eastern crossing)
- Install rebar, form and pour abutment 1 wing wall sections
Retaining Walls
Retaining Wall 104 (south of EB 23 on ramp)
- Continue to place and backfill concrete block sections
Retaining Wall 111 (along I-84, WB west of Pierpont Road)
- Excavate for leveling pad
- Continue to place concrete blocks and backfill
Retaining Wall 110 (along I-84 EB, east of EB 25 on ramp)
- Place reinforced concrete sections and backfill
Retaining Wall 113/114 (along both sides of future EB Exit 25 off ramp)
- Excavate for footing subbase
Sewer Work
Jacking Pit (under I-84 adjacent to EB 23 on ramp and WB Exit 23 off ramp)
- Install sewer behind Retaining Wall 104 (south of EB 23 on ramp)
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Excavate and place new sanitary sewer pipe
Local Roads
Reidville Drive
- Water and sewer work for culvert 003, (south of former WB Exit 24 off ramp)
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Rock Blasting
- Rock blasting to occur along Reidville Drive Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).