Construction Weekly Project Update 2/08/2016
- Bridges
- Retaining Walls
- Sewer Work
- Local Roads
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Install rebar pier 2 stemwall
- Form and pour pier 2 stem
Bridge 1224 (I-84 over Mad River, western crossing)
- Form and pour abutment 2 footing
- Construction of cofferdam and pile driving for abutment 1
Bridge 5774 (Future I-84 over Mad River, eastern crossing)
- Install rebar, form and pour abutment 1 wing wall sections
Bridge 6284 (EB Exit 25 off ramp over Mad River)
- Continue to form and pour wing walls
Retaining Walls
Retaining Wall 104 (south of EB 23 on ramp)
- Excavate for and install Temporary Earth Retaining System (TERS)
- Continue to place and backfill concrete block sections
Retaining Wall 111 (along I-84, WB west of Pierpont Road)
- Continue to place concrete blocks and backfill
- Excavate for leveling pad
Retaining Wall 110 (along I-84 EB, east of EB 25 on ramp)
- Form and pour leveling pad
- Place reinforced concrete sections and backfill
Sewer Work
Jacking Pit (under I-84 adjacent to EB 23 on ramp and WB Exit 23 off ramp)
- Install sewer behind Retaining Wall 104 (south of EB 23 on ramp)
I-84 Exit 25 WB off ramp – Scott Rd/Beaver Pond Brook
- Excavate and place new sanitary sewer pipe
Local Roads
Plank Road East (east of WB 25 on ramp)
- Excavate for box culvert 6622
Reidville Drive
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).
Note:
There will be no rock blasting this week. It is anticipated that blasting will resume next week.