Construction Weekly Project Update 12/14/2015
- I-84
- WB 23 off ramp
- Bridges
- Retaining Walls
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
I-84
WB: Median demolition from Washington Street to Hamilton Ave. (day and night)
WB 23 off ramp
Construct new WB 23 off ramp (north of existing ramp)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour wing wall step footing
- Demolition of center existing pier (night)
Bridge 1224 (I-84 over Mad River, western crossing)
- Construction of cofferdam and pile driving for abutment 2
Bridge 5774 (Future I-84 over Mad River, eastern crossing)
- Form and pour abutment 1 footing
- Strip and backfill abutment 1 footing
Bridge 6284 (EB 25 off ramp over Mad River)
- Form and pour abutment 1 stem wall
Retaining Walls
Retaining Wall 104 (south of EB 23 on ramp)
- Excavation for, and installation of, Temporary Earth Retaining System (TERS)
- Construction
Retaining Wall 105 (along Mad River at Plank Road and Harpers Ferry Road)
Retaining Wall 111 (along I-84 WB west of Pierpont Road)
- Excavation, and form, rig, and pour leveling pad
Local Roads
Harpers Ferry Road
- Harpers Ferry Road closed between Plank Road and Ashmun Street (to open before 12/25/2015)
- Water and sewer work continues
Reidville Drive
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Rock Blasting
- Rock blasting to occur along Reidville Drive, Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).