Construction Weekly Project Update 11/30/2015
- I-84
- WB 23 off ramp
- Bridges
- Retaining Walls
- Local Roads
- Rock Blasting
- Waste Stockpile Area (WSA)
I-84
- EB and WB: Line striping for roadway improvements prior to winter (night)
- WB: Median demolition from Washington Street to Hamilton Ave.
WB 23 off ramp
Construct new WB 23 off ramp (north of existing ramp)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Construction of south abutment, stem wall, and wing wall (western portion)
- Continue construction of southern pier
- Demolition of western portion of existing pier
Bridge 1224 (I-84 over Mad River, western crossing)
- Construction of cofferdam and begin to drive piles for abutment 1
Bridge 5774 (Future I-84 over Mad River, eastern crossing)
Bridge 6284 (EB 25 off ramp over Mad River)
- Form and pour abutment 1 stem wall
Retaining Walls
Retaining Wall 104 Construction (south of EB 23 on ramp)
Retaining Wall 105 Construction (along Mad River at Plank Road and Harpers Ferry Road)
Retaining Wall 111 Excavation (I-84 WB west of Pierpont Road)
Local Roads
Harpers Ferry Road
- Harpers Ferry Road closed between Plank Road and Ashmun Street
- Water and sewer work continues
Reidville Drive
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Rock Blasting
- Rock blasting to occur along Reidville Drive, Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).