Construction Weekly Project Update 11/16/2015
- I-84 EB and WB
- WB 23 off ramp
- Bridges
- Retaining Walls
- Local Roads
- Pipe Jacking
- Rock Blasting
- Waste Stockpile Area (WSA)
I-84 EB and WB
- Mill and pave for roadway improvements prior to winter (night)
- Shift traffic towards median east of Scott Road to allow outside widening and reconstruction to commence
WB 23 off ramp
Construct new WB 23 off ramp (north of existing ramp)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Construction of south abutment, stem wall, and wing wall (western portion)
- Continue construction of southern pier
Pedestrian Bridge (Over Mad River, south of Hamilton Park)
- Rig and set new pedestrian bridge
Bridge 1224 (I-84 over Mad River, western crossing)
- Excavate for, and install, temporary earth retaining system, abutment 1 and 2
Bridge 5774 (Future I-84 over Mad River, eastern crossing)
- Drive piles for abutment 1
Bridge 6284 (EB 25 off ramp over Mad River)
- Form and pour abutment 1 stem wall
Retaining Walls
Retaining Wall 104 construction (south of EB 23 on ramp)
Local Roads
Harpers Ferry Road
- Harpers Ferry Road closed between Plank Road and Ashmun Street
- Water and sewer work continues
Reidville Drive
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Pipe Jacking
Install cofferdam and excavate for reaction wall
Rock Blasting
- Rock blasting to occur along Reidville Drive, Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).