Construction Weekly Project Update 10/19/2015
I-84
WB 23 off ramp
Bridges
Retaining Walls
Local Roads
Sewer Pipe Under I-84
Rock Blasting
Waste Stockpile Area (WSA)
I-84
I-84 WB – Shoulder paving – Washington Ave. to Hamilton Avenue
I-84 median – Harpers Ferry Rd. to Austin Rd.
- Place permanent barrier (night work)
- Full-depth roadway excavation
WB 23 off ramp
Construct new WB 23 off ramp (north of existing ramp)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Construction of south abutment, stem and wing walls (western portion)
- Continue construction of southern pier
Pedestrian Bridge (over Mad River south of Hamilton Park)
- Remove existing pedestrian bridge
- Rig and set new pedestrian bridge
Bridge 5774 (new I-84 over Mad River – eastern crossing)
- Drive piles for abutment 1
Bridge 6284 (EB 25 off ramp over Mad River)
- Complete pile driving for foundation at abutment 1
- Form and pour abutment 1
Bridge 1224 (I-84 western crossing over Mad River)
- Demolition of existing superstructure (night work)
- Excavate temporary earth retaining system
Retaining Walls
Retaining Wall 104 construction (south of EB 23 on ramp)
Retaining Wall 105 construction (north side of Plank Rd. culvert)
Local Roads
Plank Road
Harpers Ferry Road
- Harpers Ferry Road closed between Plank Road and Ashmun Street
- Harpers Ferry Road detour in place
- Water and sewer work
Reidville Drive
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Sewer Pipe Under I-84
Jack ductile pipe for new sewer pipe under I-84, east of Hamilton Avenue.
Rock Blasting
- Rock blasting to occur along Reidville Drive, Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).