Construction Weekly Project Update 10/12/2015
- I-84
- WB 23 off ramp
- Bridges
- Retaining Walls
- Local Roads
- Sewer Pipe Under I-84
- Rock Blasting
- Waste Stockpile Area (WSA)
I-84
I-84 WB – Shoulder paving – Washington Ave. to Hamilton Avenue
I-84 median Harpers Ferry Rd. to Austin Rd. – Place permanent barrier (night work)
WB 23 off ramp
Construct new WB 23 off ramp (north of existing ramp)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Construction of south abutment, stem and wing walls (western portion)
- Continue construction of southern pier
Bridge 5774 (new I-84 over Mad River – eastern crossing)
- Drive test piles for abutment 1
Bridge 6284 (EB 25 off ramp over Mad River)
- Drive pile for foundation at abutment 1
Bridge 1226 (Harpers Ferry Road over I-84)
Bridge 1224 (I-84 western crossing over Mad River)
- Demolition of existing superstructure (night work)
Retaining Walls
Retaining Wall 104 construction (south of EB 23 on ramp)
Retaining Wall 105 construction (north side of Plank Rd. culvert)
Local Roads
Plank Road
- Continue to build roadway over box culvert
- Excavate, form, and pour wing walls east of culvert
- Detour in place between Harpers Ferry Road and White Oak Lane
Reidville Drive
- One lane closed intermittently with alternating traffic
- Excavation and trucking of materials
Sewer Pipe Under I-84
Establish connections in receiving pit for new sewer pipe under I-84, east of Hamilton Avenue.
Rock Blasting
- Rock blasting to occur along Reidville Drive, Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).