Images go here.
I-84 EB/WB – Temporary illumination exit 23 off ramp near Retaining Wall 112
I-84 median Harpers Ferry Road to Austin Road – Excavation, drainage, install lighting conduit, reconstruction of inside shoulders
Construct new WB 23 off ramp (north of existing ramp)
Bridge 4321 (Hamilton Avenue over I-84)
Bridge 5774 (new I-84 over Mad River – eastern crossing)
Bridge 6284 (EB 25 off ramp over Mad River)
Bridge 1226 (Harpers Ferry Road over I-84)
Bridge 1224 (I-84 western crossing over Mad River)
Retaining Wall 104 construction (south of EB 23 on ramp)
Plank Road
Reidville Drive
Continue jacking of new sewer pipe under I-84, east of Hamilton Avenue.
Rock blasting to occur west of Hamilton Avenue, Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
Rock blasting to occur along Reidville Drive, Tuesday, Wednesday, and Thursday intermittently between 9:30 AM and 11:30 AM.
Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing).