Construction Weekly Project Update 08/03/2015

I-84

I-84 EB west of Hamilton Avenue – Construct outside widening and shoulders
I-84 median Harpers Ferry Road to Austin Road – Excavation, drainage, install lighting conduit, reconstruction of inside shoulders
I-84 west of Harpers Ferry Road – Place fill, construct roadway

WB 23 off ramp

Construct new WB 23 off ramp (north of existing ramp)

Bridges

Bridge 4321 (Hamilton Avenue over I-84)

Bridge 6284 (EB 25 off ramp over Mad River)

Pedestrian Bridge (across Mad River)

Temporary Haul Bridge (across Mad River)

Retaining Walls

Retaining Wall 104 construction (south of EB 23 on ramp)
Retaining Wall 112 construction (along EB 23 off ramp)

Local Roads

Plank Road

Reidville Drive

Jacking of Sewer Pipe Under I-84

Continue jacking of new sewer pipe under I-84, east of Hamilton Avenue.

Rock Blasting

Rock blasting to occur west of Hamilton Avenue, Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM.
Rock blasting to occur along Reidville Drive, Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM.
Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.

Waste Stockpile Area (WSA)

Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility.