Construction Weekly Project Update 4/22/2019
I-84 EB & WB – Lane closures possible 9:00 AM – 3:00 PM, Tuesday through Friday, for median and shoulder work:
- Lighting, sign, and fence installation
- Metal beam rail installation
- Drainage work
- Landscaping
- Touch-up painting of bridges
Local Roads
- Drainage work
- Guide rail installation
- Sand removal/sweeping
No Night Work
Temporary Reuse Stockpile Area (TRSA)
- Excavation, landscaping and trucking of excavated material
Facing north, I-84 and Harpers Ferry Road Bridge, with new Plank Road East, westbound on-ramp, and Plank Road, north of I-84.