Construction Weekly Project Update 12/03/2018
- Bridges
- Retaining Walls
- Local Roads
- I-84
- Miscellaneous Work Project-wide
- Lane Closures
- Waste Stockpile Area (WSA)
Bridges
Project-wide
- Miscellaneous bridge work
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Prep and demolish former WB I-84 bridge
Bridge 1228 (The Scott Rd Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)
Retaining Walls
Retaining Wall 121 (East Main Street, west of Scott Road)
- Complete driveway and sidewalk
Local Roads
Reidville Drive
- Install topsoil EB slope: install temporary barrier
- Pave top course
Scott Road (from East Main Street to Reidville Drive)
Harpers Ferry Road (south of Bridge)
I-84 EB and WB
- Install overhead- and side-mounted signs – traffic stoppages (15 minutes)
Miscellaneous work – Various Locations Project-wide
- Fence installation
- Environmental and river work – Mad River final finish work
- Install guide rail
- Grade slopes
- Install permanent embedded pavement markings (night)
- Plant trees
- Install bridge joints
- Install pedestrian paths
- Install fiber optics cables
- Install fire suppression system
Lane Closures
Daytime: Lane closures possible from 9:00 AM to 3:00 PM on eastbound and westbound I-84 for:
- Miscellaneous guide rail/fence/sign installation
Night work: Lane closures; possible delays: One lane may be open between 9:00 PM and 6:00 AM; two lanes will be open from 8:00 PM to 9:00 PM, Sunday through Friday nights
- Miscellaneous barrier moves
- Installation of guide rail on I-84
- Reconstruction of local roads
- Permanent pavement markings
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.