Construction Weekly Project Update 11/26/2018
- Bridges
- Retaining Walls
- Local Roads
- Miscellaneous Work Project-wide
- Lane Closures
- Waste Stockpile Area (WSA)
Bridges
Project-wide
- Miscellaneous bridge work
Retaining Walls
Retaining Wall 109 (Westbound I-84 east of WB 25 off-ramp)
- Install remaining sound barrier wall
Local Roads
East Main Street/Plank Road East/Reidville Drive/Hamilton Avenue
- Driveway restoration
- Pave
- Install sidewalk
East Main Street
- Pave small commuter parking lot
Harpers Ferry Road (south of Bridge) and Washington Street (EB 23 off-ramp)
Miscellaneous work – Various Locations Project-wide
- Install overhead and side-mounted signs
- Fence installation
- Environmental and river work – Mad River final finish work
- Install guide rail
- Grade slopes
- Install permanent pavement markings
- Plant trees
- Install bridge joints
Lane Closures
Daytime: Lane closures possible from 9:00 AM to 3:00 PM on eastbound and westbound I-84 for:
- Miscellaneous guide rail/fence/signing work
Night work: Lane closures; possible delays: One lane may be open between 9:00 PM and 6:00 AM; two lanes will be open from 8:00 PM to 9:00 PM, Sunday through Friday nights
- Miscellaneous barrier moves
- Installation of guide rail on I-84
- Reconstruction of local roads
- Permanent pavement markings
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.