Construction Weekly Project Update 06/29/2015

I-84 EB
Milling and paving on I-84 EB between Harpers Ferry Road and Scott Road, and barrier placement, Monday through Wednesday, from 9:30 PM to 6:00 AM.

I-84 WB
Milling and paving on I-84 WB between Scott Road and Harpers Ferry Road, and barrier placement, Monday through Wednesday, from 9:30 PM to 6:00 AM.

Placement of temporary barrier along right shoulder west of Hamilton Avenue Bridge.

Local Roads
Hamilton Avenue Vicinity

Plank Road

Reidville Drive

Pedestrian Bridge Across Mad River
Continue construction of pedestrian bridge across Mad River south of Hamilton Park.

Rock Blasting
Rock blasting to occur along I-84 EB Exit 23 off ramp on Tuesday, Wednesday and Thursday between 9:30 AM and 11:30 AM.

Rock blasting to occur along Reidville Drive, Monday through Thursday between 9:30 AM and 11:30 AM.

Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.

Jacking of Sewer Pipe Under I-84
Continue jacking of new sewer pipe under I-84, east of Hamilton Ave.