Construction Weekly Project Update 9/17/2018
- Bridges
- Retaining Walls
- Local Roads
- I-84 Mainline
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)
- Place concrete deck
- Form and pour approach slab
- Form and pour parapet
Retaining Walls
Retaining Wall 115 (South side of future WB 25 on-ramp, west of Harpers Ferry Road)
- Set parapets
- Form and pour moment slab
Local Roads
East Main Street/Scott Road/Reidville Drive
Future Plank Road East
- Install sound barrier wall
- Roadway reconstruction (Mobil station to interim WB on-ramp)
East Main Street (west of Scott Road)
I-84 Mainline
I-84 EB
WB I-84
- Shift traffic, excavate subbase
Miscellaneous work
- Barrier moves (night)
- Mill/pave/stripe
- Fence installation
Night Work
One-lane closures possible between 7:00 PM and 6:00 AM on I-84 eastbound, and between 9:30 PM and 6:00 AM on I-84 westbound, Sunday through Friday nights
- Remove underdecking on Hamilton Avenue Bridge
- Milling/paving/striping
- Miscellaneous barrier moves
- Reconstruction of local roads: Plank Road East, East Main Street, and Reidville Drive
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.