Construction Weekly Project Update 9/03/2018
- Bridges
- Retaining Walls
- Local Roads
- I-84 Mainline
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Remove brackets and underdecking (night)
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Erect structural steel and bolt up
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)
- Set up deck finishing machine
Retaining Walls
Retaining Wall 115 (South side of future WB 25 on-ramp, west of Harpers Ferry Road)
Retaining Wall 121 (East Main Street, west of Scott Road)
- Excavate for leveling pad
- Install drainage structures
Local Roads
Harpers Ferry Road
- Install permanent signalization
Future Plank Road East
- Install sound barrier wall
- Full-depth reconstruction (Mobil station to interim WB on-ramp) (night)
I-84 Mainline
I-84 EB
WB I-84
- Milling/Paving
- Shift traffic, excavate subbase
Miscellaneous work
- Barrier moves (night)
- Mill/pave/stripe
- Fence installation
Night Work
One-lane closures possible between 9:30 PM and 6:00 AM, Tuesday through Friday nights
No lane closures over Labor Day weekend
- Remove underdecking on Hamilton Avenue Bridge
- Milling/paving/striping
- Miscellaneous barrier moves
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.