Construction Weekly Project Update 06/15/2015

I-84 WB
Milling and paving between Harpers Ferry Road and Hamilton Avenue. Lane closures will occur from Exits 25A-22, Monday through Friday, from 9:30 PM to 6:00 AM.

I-84 EB
Milling and paving between Hamilton Avenue and Scott Road. Lane closures will occur from Exits 22-25A, Monday through Friday, from 9:30 PM to 6:00 AM.

Local Roads
Hamilton Avenue Vicinity

Plank Road

Reidville Drive

Pedestrian Bridge Across Mad River
Continue construction of pedestrian bridge across Mad River south of Hamilton Park.

I-84 WB Exit 25A On Ramp Area
Tree clearing.

Rock Blasting
Rock blasting to occur along I-84 EB Exit 23 off ramp and Reidville Drive off ramp on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM.
Traffic stoppages on I-84, Hamilton Ave., Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.

Jacking of Sewer Pipe Under I-84
Continue jacking of new sewer pipe under I-84, east of Hamilton Ave.