Construction Weekly Project Update 6/11/2018
- Bridges
- Culverts
- Retaining Walls
- Local Roads
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Form and pour concrete sidewalk and south abutment approach slab
Bridge 1226 (Harpers Ferry Road Bridge)
- Install fencing – west side
- Install cantilever sign foundation
Bridge 6590 (Future EB 23 on-ramp, east of Hamilton Avenue Bridge)
- Install sidewalk and parapet tie-ins
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Form and pour abutment 2 footing
- Install sanitary sewer pipe sleeve
- Mad River relocation
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge by Public Act 17-230 section 34)
- Form and pour abutments 1 and 2 stems and wing walls
Culverts
Culvert 1227 (Under I-84, east of Harpers Ferry Road)
- Prep for water handling and excavation
Retaining Walls
Retaining Wall 115 (South side of future WB 25 on-ramp, west of Harpers Ferry Road)
- Excavate for, and form and pour leveling pad
- Rig and set concrete blocks
Retaining Walls 102 and 103 (On both sides of future EB 23 on-ramp)
- Grade; install subbase material and tie-in with EB 23 on-ramp bridge
Local Roads
Pierpont Road
I-84 Mainline
WB I-84
WB 25 off-ramp (former off-ramp to Scott Road)
- Water work in Beaver Pond Brook
Miscellaneous work project-wide
- Plant trees and seed slopes project-wide
- Temporary barrier moves (night)
- Install permanent signalization at Hamilton Avenue and Scott Road
- Install barrier caps
Night Work (One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Thursday nights)
- Miscellaneous work, including barrier moves, project-wide
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.