Construction Weekly Project Update 5/28/2018
- Bridges
- Retaining Walls
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Concrete closure pour for bridge deck
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Drive cofferdam and piles for abutment 2
- Temporarily relocate Mad River
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge by Public Act 17-230 section 34)
- Form and pour abutments 1 and 2 stems and wing walls
Retaining Walls
Retaining Wall 119 (WB I-84 along future Plank Road East)
- Install leveling pad
- Rig and set concrete blocks
Retaining Wall 115 (South side of future WB 25 on-ramp, west of Harpers Ferry Road)
- Excavate for, and form and pour leveling pad
I-84 Mainline
WB I-84
WB 25 off-ramp (former off-ramp to Scott Road)
- Water work in Beaver Pond Brook
Miscellaneous work project-wide
- Plant trees and seed slopes project-wide
Night Work (One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Thursday nights)
- Miscellaneous work project-wide
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.