Construction Weekly Project Update 5/14/2018
- Bridges
- Retaining Walls
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Continue to place concrete for bridge deck
Bridge 1226 (Harpers Ferry Road Bridge)
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Form and pour abutment 1 wingwall
- Drive cofferdam and piles for abutment 2
- Partially demolish EB 25 off-ramp deck
- Temporarily relocate Mad River
Bridge 1228 (Scott Road Bridge which will be renamed the Najla G. Noujaim
Memorial Bridge)
- Form and pour abutment 1 footing
- Form and pour abutment 2 stems
Retaining Walls
Retaining Wall 119 (WB I-84 along future Plank Road East)
I-84 Mainline
WB I-84
WB 25 off-ramp (former off-ramp to Scott Road)
- Demolish existing culvert
Miscellaneous work project wide
- Install overhead sign foundations at Washington Street/Hamilton Avenue
- Install permanent signalization at Hamilton Avenue and Scott Road
Night Work (One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Thursday nights)
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.