Construction Weekly Project Update 4/09/2018
- Bridges
- Retaining Walls
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Install rebar and shear studs for bridge deck
Bridge 1226 (Harpers Ferry Road Bridge)
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Form and pour abutment stem and wing walls
- Temporarily relocate Mad River
Bridge 1228 (Scott Road Bridge)
- Install support of excavation, and excavate for abutments 1 and 2
- Line drilling (in preparation for blasting) at abutment 1
- Form and pour abutment 2 footing
Retaining Walls
Retaining Wall 106 (north of WB I-84, west of WB 25 on-ramp)
- Install fence on top of wall
Retaining Wall 119 (WB I-84 along future Plank Road East)
- Form and pour moment slab
I-84 Mainline
WB I-84 (Approaches to future I-84 bridge over the Mad River west of Harpers Ferry Road)
- Formation of subgrade roadway
EB I-84
- Remove former EB I-84 pavement (night work)
WB 25 off-ramp (former off-ramp to Scott Road)
WB 25A on-ramp
- Install sound barrier wall
- Hang overhead signs
Miscellaneous work project wide
- Install median conduit, wires, and lights
Night Work (One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Thursday nights)
- Remove former EB I-84 pavement
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.