Construction Weekly Project Update 4/02/2018
- Bridges
- Retaining Walls
- I-84
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Install rebar for bridge deck
Bridge 1226 (Harpers Ferry Road Bridge)
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Set granular fill
- Form stem wall at abutment 1
- Begin excavation of Mad River
Bridge 1228 (Scott Road Bridge)
- Install support of excavation, and excavate for abutments 1 and 2
- Form and place rebar for center pier stem
- Line drilling (in preparation for blasting) at abutment 1
Retaining Walls
Retaining Wall 119 (WB I-84 along future Plank Road East)
- Form and pour moment slab
Retaining Wall 102 (EB I-84 along EB 23 on-ramp)
- Form and pour moment slab
I-84 Mainline
WB I-84 (Approaches to future I-84 bridge over the Mad River west of Harpers Ferry Road)
- Formation of subgrade roadway
WB 25 off-ramp (former off-ramp to Scott Road)
- Blast rock (see Rock Blasting section below for further information)
- Install sanitary sewer
WB 25A on-ramp
- Install sound barrier wall
- Hang overhead signs
Night Work (One-lane closures possible between 9:30 PM and 6:00 AM, Sunday through Thursday nights)
- Demolition of Scott Road Bridge
- Miscellaneous barrier moves
Rock Blasting
- Rock blasting to occur along former WB 25 off-ramp: When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM.
- Traffic stoppages on I-84, WB 25 off-ramp, Scott Road, Plank Road East, East Main Street and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.