Construction Weekly Project Update 2/26/2018
- Bridges
- Retaining Walls
- I-84
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Install overhang brackets and underdecking (night work)
Bridge 6591 (Future WB 25 on-ramp, east of Harpers Ferry Road)
Bridge 1228 (Scott Road Bridge)
- Demolish deck of western portion of bridge (night work)
Retaining Walls
Retaining Wall 106 (north of WB I-84, west of WB 25 on-ramp)
- Backfill, and grade slope
I-84 Mainline
WB I-84 (Approaches to bridge over the Mad River west of Harpers Ferry Road)
WB I-84 (from east of Harpers Ferry Road to west of Scott Road)
- Median work: Set median barrier, conduit and light pole foundations
WB 25 off-ramp (former off-ramp to Scott Road)
WB 25A on-ramp
- Drill foundations for sound barrier wall
Miscellaneous Work Locations
- Pothole repair (night work)
- Install median drainage, and median conduit and wires
Night Work
- Demolish deck of western portion of Scott Road Bridge
- Pothole repair
- Install overhang brackets and underdecking on Hamilton Avenue Bridge
Rock Blasting
- Rock blasting to occur along former WB 25 off-ramp. When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.
- Traffic stoppages on I-84, WB 25 off-ramp, Scott Road, Plank Road East, East Main Street and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.