Construction Weekly Project Update 2/12/2018
- Bridges
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Erect structural steel and bolt up (see Night Work section below for more info)
- Install overhanging brackets under decking
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Excavate and drive cofferdam piles
- Drive piles abutment 1
Bridge 1228 (Scott Road Bridge)
- Demolish deck of western portion of bridge (night work)
I-84 Mainline
EB I-84 (from east of Harpers Ferry Road to west of Scott Road)
- Formation of subgrade roadway
WB 25 off-ramp (former off-ramp to Scott Road)
- Pipework/install sewer bypass
- Prepare for rock blasting
I-84 Median (WB 25 on-ramp vicinity)
WB 25A on-ramp
- Drill foundations for sound barrier wall
Miscellaneous Work Locations
- Pothole repair (night work)
- Install median drainage, and median conduit and wires
Night Work
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.