Construction Weekly Project Update 1/29/2018
- Bridges
- I-84
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge)
- Begin steel erection and bolt up (see Night Work section below for more info)
Bridge 6591 (Future WB 25 on-ramp, west of Harpers Ferry Road)
- Excavate and drive cofferdam piles
- Drive piles abutment 1
Bridge 1228 (Scott Road Bridge)
- Demolish deck of western portion of bridge (night work)
- Remove temporary overhead wires
I-84 Mainline
EB I-84 (from east of Harpers Ferry Road to west of Scott Road)
- Remove existing I-84 EB roadway pavement
WB 25 off-ramp (former off-ramp to Scott Road)
- Remove existing WB 25 off-ramp pavement; excavate to rock
EB 25 off-ramp (former off-ramp to Harpers Ferry Road)
- Remove existing EB I-84 roadway pavement
- Pipework/install sewer bypass
I-84 Median (from WB 25 off-ramp vicinity to Hamilton Avenue)
WB 25A on-ramp
- Drill foundations for sound barrier wall
Miscellaneous Work Locations
- Pothole repair
- Median Drainage
Night Work
- Demolish deck of western portion of Scott Road Bridge
- Steel erection on Hamilton Avenue Bridge; 10-minute stoppages may occur on
WB I-84 for safety, between 11:00 PM and 5:00 AM
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.