Construction Weekly Project Update 12/18/2017
- Bridges
- I-84
- Retaining Walls
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 6590 (EB 23 on ramp)
- Form and pour parapets
- Form and cover parapets
Bridge 1226 (Harpers Ferry Road Bridge)
- Form and pour parapets and sidewalks
- Form and cover parapets
- Install anchor bolt bearings abutment 1
Bridge 1228 (Scott Road Bridge)
- Demolish deck of western portion of bridge (night work)
Retaining Walls
Retaining Wall 102 (along future EB 23 on-ramp)
I-84 Mainline
I-84 Eastbound Mainline – (I-84 bridge over Mad River eastern crossing to Culvert 02537 – Beaver Pond Brook under I-84)
- Form and pour median barrier cap
I-84 Westbound – west of Scott Road Bridge
- Shift traffic along Retaining wall 108
Miscellaneous Work Locations on Mainline
Night Work
- Demolish deck of western portion of Scott Road Bridge
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.