Construction Weekly Project Update 11/20/2017
- Bridges
- I-84
- Retaining Walls
- Local Roads
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue Bridge over I-84)
Bridge 6590 (EB 23 on ramp)
Bridge 1226 (Harpers Ferry Road Bridge)
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour EB stage 3 approach slabs
Bridge 5774 (future I-84 bridge over Mad River)
- Form and pour east and west approach slab for WB deck
Bridge 1228 (Scott Road Bridge)
- Install salt guard and stripe
Retaining Walls
Retaining Wall 107 (along EB I-84 west of Scott Road Bridge)
- Form and pour footings
- Rig and set wall/parapet
Retaining Wall 118 (along EB I-84 east of Harpers Ferry Road and new Culvert 1227)
- Form and pour moment slab
I-84 Mainline
I-84 east of WB 25 on-ramp (Culvert 02537; Beaver Pond Brook under I-84)
- Form and pour walls and roof
I-84 EB Mainline – (Culvert 02537 vicinity)
- Place subgrade material and pave
WB 25A on-ramp
- Drill foundations for sound barrier wall
Miscellaneous Work Locations on Mainline
- Install drainage
- Install concrete cap on median
Local Roads
Various Locations Project-wide
- Install fencing
- Install permanent and temporary illumination median conduit
East Main Street and Scott Road
- Fill roadway/grade/pave from Scott Road Bridge to East Main Street
Reidville Drive
- Install temporary signalization Reidville Drive/Scott Road
- Excavate existing overburden of earth north of Reidville Drive
- Excavate Harpers Ferry Road detour
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.