Construction Weekly Project Update 10/30/2017
- Bridges
- I-84
- Retaining Walls
- Local Roads
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 6590 (EB 23 on ramp)
- Install concrete deck (second and third placement)
Bridge 1226 (Harpers Ferry Road Bridge)
- Form and pour sidewalk and parapets
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour concrete closure
Bridge 1228 (Scott Road Bridge)
Retaining Walls
Retaining Wall 102 & 103 (on both sides of EB 23 on-ramp)
- Form and pour leveling pad
- Backfill and set remaining wall panels
Retaining Wall 107 (along EB I-84 west of Scott Road Bridge)
Retaining Wall 118 (along EB I-84 east of Harpers Ferry Road and new Culvert 1227)
- Rig and set parapet
- Form and pour moment slab
I-84 Mainline
I-84 east of WB 25 on-ramp (Culvert 02537; Beaver Pond Brook under I-84)
- Saw cut and demolish existing culvert
- Set up water handing
- Form and pour slab on grade
Harpers Ferry Road to Culvert 2537 (east of WB 25 on-ramp)
Eastbound Mainline – Hamilton Avenue to Harpers Ferry Road
WB 25A on-ramp
- Drill foundations for sound barrier wall
Miscellaneous Work Locations on Mainline
- Drainage
- Concrete cap on median
I-84 east of WB 25 on-ramp (Culvert 02537; Beaver Pond Brook under I-84)
- Install support of excavation and excavate for demolition
Local Roads
Various Locations Project-wide
- Install fencing
- Install permanent and temporary illumination median conduit
Reidville Drive
- Excavate existing overburden of earth north of Reidville Drive
- Excavate Harpers Ferry Road detour
- Drill and blast rock
Scott Road/Plank Road
Rock Blasting
- Blasting will be permitted Monday through Friday from 9:00 am to 3:00 pm.
- Motorists may experience brief stoppages on I-84, within the work area, Tuesday, Wednesday, and Thursday between 9:30 am and 11:30 am.
- Traffic stoppages on Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Night Work
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.