Construction Weekly Project Update 9/25/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour pier 2 stem
- Construct abutment 2 backwall
Bridge 6590 (EB 23 on ramp)
- Install stay-in-place forms and shear studs
Bridge 1226 (Harpers Ferry Road Bridge)
- Excavate, form and pour south approach slab
Bridge 5774 (future I-84 bridge over Mad River)
- Form and pour EB deck parapets
- Form and pour eastern deck approach slabs
Bridge 6284 (EB 25 off ramp)
Bridge 1228 (Scott Road Bridge)
- Install deck rebar
- Set deck finishing machine and test run
Retaining Walls
Retaining Wall 119 (along WB I-84 east of Harpers Ferry Road)
- Grade in front of Retaining wall 119; set barrier
I-84 Mainline
- Install subbase material in front of Retaining Wall 119
- Pave median opposite WB 25 on-ramp vicinity (night work)
- Install drainage structures in I-84 median between Hamilton Avenue Bridge and future EB 23 on-ramp
- Fine grade and prep subbase material at future path for I-84 west of Harpers Ferry Road
Local Roads
Various Locations Project-wide
- Miscellaneous conduit work
- Turf establishment
Reidville Drive
- Excavate existing overburden of earth north of Reidville Drive
- Drill and blast rock
East Main Street
- Install underground utilities – Scott Road vicinity (along northern side of East Main Street from commuter lot east of Scott Road intersection, to west of intersection) (night)
- Install permanent signalization for East Main Street and Scott Road
Night Work
- Underground utilities installation – East Main Street
- Pave median opposite WB 25 on-ramp vicinity
- Install drainage structures in I-84 median between Hamilton Avenue Bridge and future EB 23 on-ramp
Rock Blasting
- Blasting will be permitted Monday through Friday from 9:00 am to 3:00 pm.
- Motorists may experience brief stoppages on I-84, within the work area, Tuesday, Wednesday, and Thursday between 9:30 am and 11:30 am.
- Traffic stoppages on Harpers Ferry Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.