Construction Weekly Project Update 9/4/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Excavate and pour pier 2 stem
- Construct abutment 1 and 2 backwall
Bridge 6590 (EB 23 on ramp)
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour WB parapet
- Excavate, form and pour eastern approach slab for WB deck
Bridge 6284 (future EB 25 off ramp)
Bridge 1228 (Scott Road Bridge)
- Complete wingwall parapet
- Install studs
Retaining Walls
Retaining Wall 118 (along EB I-84 east of Harpers Ferry Road and new culvert 1227)
- Rig and set precast concrete blocks
Retaining Wall 119 (along WB I-84 east of Harpers Ferry Road)
- Rig and set precast concrete blocks
I-84
I-84
- Install overhead sign foundation
- Install drainage structures in front of Retaining Wall 119
WB I-84 (Bridge 1224 vicinity)
- Cut and fill to subgrade
- Install drainage and subbase material
Local Roads
Various Locations Project-wide
Reidville Drive
- Excavate existing overburden of earth north of Reidville Drive
- Culvert 1227 (east of rock cut and under I-84) – backfill
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.