Construction Weekly Project Update 8/28/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Excavate and pour pier 2 footing
- Construct abutment 1 and 2 backwall
Bridge 6590 (EB 23 on ramp)
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour WB parapet
- Excavate, form and pour eastern approach for WB deck
- Excavate, form and pour western approach for EB 25 off-ramp
Bridge 6284 (future EB 25 off ramp)
- Apply touch-up paint on girders
Bridge 1226 (Harpers Ferry Road Bridge)
- Install rebar on bridge deck
- Set deck finishing machine and test run
- Begin to pour concrete deck
Bridge 1228 (Scott Road Bridge)
- Install stay-in-place forms
- Complete wingwall parapet
- Encase ductbanks
Retaining Walls
Retaining Wall 118 (along EB I-84 east of Harpers Ferry Road and new culvert 1227)
- Rig and set precast concrete blocks
Retaining Wall 119 (along WB I-84 east of Harpers Ferry Road)
- Rig and set precast concrete blocks
I-84
I-84
- Install overhead sign foundation
- Install drainage structures in front of Retaining Wall 119
WB I-84 (Bridge 1224 vicinity)
Local Roads
Reidville Drive
- Excavate existing overburden of earth north of Reidville Drive
- Culvert 1227 (east of rock cut and under I-84) – backfill
East Main Street
- Install underground utilities – Scott Road vicinity (along northern side of East Main Street from commuter lot east of Scott Road intersection, to west of intersection) (Night)
Night Work
- Underground utilities installation – East Main Street
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.