Construction Weekly Project Update 8/21/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour pier 1 stem
- Excavate and pour pier 2 footing
- Construct abutment 2 backwall
Bridge 6590 (EB 23 on ramp)
- Post-tension pier cap
- Complete abutment backwalls
- Begin delivery of steel girders
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour WB parapet
- Excavate, form and pour western approach
- Place membrane waterproofing on EB 25 off ramp approach slab
Bridge 6284 (future EB 25 off ramp)
- Apply touch-up paint on girders
Bridge 1226 (Harpers Ferry Road Bridge)
- Install rebar on bridge deck
- Set deck finishing machine and test run
Bridge 1228 (Scott Road Bridge)
- Form and pour backwalls at abutment 1 & 2
Retaining Walls
Retaining Wall 118 (along EB I-84 east of Harpers Ferry Road and new culvert 1227)
- Excavate and place concrete for leveling pad
- Rig and set precast concrete blocks
Retaining Wall 119 (along WB I-84 east of Harpers Ferry Road)
- Excavate for, and form and pour leveling pad
- Rig and set precast concrete blocks
I-84
I-84
- Install overhead sign foundation
- Install drainage structures in front of Retaining Wall 119
I-84 East-end (from end of EB 25 on ramp to end of Project limits at Pierpont Road)
WB I-84 (Bridge 1224 vicinity)
Local Roads
Reidville Drive
- Culvert 1227 (east of rock cut and under I-84) – Install wingwall ties for Retaining wall 118, and membrane waterproofing
Reidville Drive/Harpers Ferry Road/EB 25 off ramp
East Main Street
- Install underground utilities – Scott Road vicinity (along northern side of East Main Street from commuter lot east of Scott Road intersection, to west of intersection) (Night)
Plank Road East (adjacent to existing WB 25 on ramp, along west end of Retaining Wall 106)
- Install temporary signalization at Plank Road East/Scott Road/WB 25 off ramp
Night Work
- Underground utilities installation – East Main Street
- Pave from end of EB 25 on ramp to end of Project limits at Pierpont Road
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.