Construction Weekly Project Update 8/14/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour pier 1 stem
- Excavate and pour pier 2 footing
- Construct abutment 2 backwall
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour WB parapet
- Excavate, form and pour western approach
Bridge 6284 (future EB 25 off ramp)
- Install bridge joints
- Weld bearings
Bridge 1226 (Harpers Ferry Road Bridge)
- Install rebar on bridge deck
- Set deck finishing machine and test run
Bridge 1228 (Scott Road Bridge)
- Form and pour backwalls at abutment 1 & 2
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
Retaining Wall 118 (along EB I-84 east of Harpers Ferry Road and new culvert 1227)
- Excavate and place concrete for leveling pad
Retaining Wall 119 (along WB I-84 east of Harpers Ferry Road)
- Excavate for, and form and pour leveling pad
- Rig and set blocks
I-84
I-84
- Install overhead sign foundation
Local Roads
Reidville Drive
- Culvert 1227 (east of rock cut and under I-84) – Install, closure pour and chimneys, and wingwall ties for Retaining wall 118
- Reidville Drive/Harpers Ferry Road/EB 25 off ramp – Install temporary signalization
East Main Street
- Install underground utilities – Scott Road vicinity (along northern side of East Main Street from commuter lot east of Scott Road intersection, to west of intersection) (Night)
Plank Road East (adjacent to existing WB 25 on ramp, along west end of Retaining Wall 106)
- Install temporary signalization at Plank Road East/Scott Road/WB 25 off ramp
Night Work
- Underground utilities installation – East Main Street
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.