Construction Weekly Project Update 7/24/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour abutment 2 wingwalls
Bridge 6590 (EB 23 on ramp)
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Install rebar for bridge deck
Bridge 1226 (Harpers Ferry Road Bridge)
- Install rebar for bridge deck
Bridge 6284 (future EB 25 off ramp)
- Form and pour wingwall 2 stem
- Form and pour approach slab abutment 2
- Form and pour parapets abutment
- Backfill abutment 2
Retaining Walls
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Rig and set blocks, east end
I-84
I-84 WB (WB Exit 25 off ramp)
- Continue to construct sound barrier wall
I-84 EB (from EB 25 on ramp to Pierpont Road)
Local Roads
Reidville Drive
- Culvert 1227 (east of rock cut and under I-84) – Install headwall, closure pour and chimneys
- Install temporary signalization at Reidville Drive/Harpers Ferry Road
Future Plank Road East (adjacent to existing WB 25 on ramp, along west end of Retaining Wall 106)
- Install drainage structures in pipes in Bryan Street vicinity
- Install temporary signalization at Plank Road East/Scott Road/WB 25 off ramp
East Main Street
- Install underground utilities – Scott Road vicinity (along northern side of East Main Street from commuter lot east of Scott Road intersection, to west of intersection) (Night)
Night Work
- Underground utilities installation – East Main Street
- Barrier moves
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.