Construction Weekly Project Update 7/03/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
- Holiday Work Schedule
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour pier 1 stems
- Form and pour abutment 1 & 2 stem
Bridge 6590 (EB 23 on ramp)
- Pour and form wingwall stems, and pier cap
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Set structural steel and bolt up
- Install overhang brackets
- Backfill and grade east/west approach to bridge
Bridge 6284 (future EB 25 off ramp)
- Form and pour wingwall 2 stem wall, and footing
- Form and pour parapets
Bridge 1228 (Scott Road Bridge)
- Install utilities at underground approaches to bridge
Retaining Walls
Retaining Wall 101 (along WB I-84 and east of WB 23 off ramp)
Install moment slab
Retaining Wall 102 and 103 (along both sides of EB 23 on ramp)
- Backfill and set precast wall panels
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation
- Form and pour leveling pad, east end
- Rig and set blocks, east end
I-84
I-84 Mainline; WB Hamilton Avenue to WB 23 off ramp
- Grade and box out roadway for widening
Future EB 23 on ramp, east of Hamilton Avenue
- Install sound barrier wall
EB 23 off ramp
- Remove graffiti on sound barrier wall
I-84 EB – from EB 25 on ramp to Pierpont Road
- Install drainage pipe and structures
Local Roads
Reidville Drive
- Culvert 1227 (east of rock cut and under I-84) – Form and pour culvert formwork at inlet
Future Plank Road East (adjacent to existing WB 25 on ramp, along west end of Retaining Wall 106)
- Cut to subgrade
- Culvert 02537 (Beaver Pond Brook under I-84, south of WB 25 on ramp) Complete parapet and moment slab for Retaining Wall 108
Night Work
- No night work on the project this week.
- Night work will resume Sunday, July 9 at 9:30 PM.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.
Holiday Work Schedule
No Lane Closures are Scheduled on the I-84 Waterbury Project in Observance of the Fourth of July Weekend.
- No work will be performed on the Project from Saturday, July 1 through Tuesday, July 4.
- Day shift will resume on Wednesday morning, July 5.
- Night shift with potential lane closures on I-84 will resume on Sunday, July 9 at 9:30 PM
- Only work of an emergency nature will be considered.