Construction Weekly Project Update 6/12/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour abutment 2 footing
- Form and pour pier 1 stem
- Form and pour abutment 1 stem
Bridge 6590 (EB 23 on ramp)
- Pour and form abutment 1 stems and pier cap
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Set structural steel
- Backfill and grade east approach to bridge
Bridge 1226 (Harpers Ferry Road Bridge)
- Install stay in place forms
- Form and pour wingwall footing
Bridge 6284 (future EB 25 off ramp)
- Backfill abutment 2
- Set deck paving machine and run test
- Pour concrete deck
- Form and pour wingwall 2 stem wall
Bridge 1228 (Scott Road Bridge)
- Install utilities across bridge
Retaining Walls
Retaining Wall 102 and 103 (along both sides of EB 23 on ramp)
- Backfill and set precast wall panels
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation (day and night work)
I-84
- WB 25 interim on ramp (just east of existing entry ramp)
Grade, place subgrade, pave (night work)
- I-84 Mainline Median
Grade and box out median from WB 25 on ramp to former WB 24 off ramp vicinity
Pave median from WB 25 on ramp to former WB 24 off ramp vicinity (night work)
- WB 25 Off Ramp
- Install sound barrier east of new WB 25 off ramp
Local Roads
Reidville Drive
- Culvert 1227 (east of rock cut and under I-84) – Excavate and prepare subgrade
Plank Road (from Cul-de-Sac to Harpers Ferry Road)
Plank Road East
- Culvert 06622 (west of Scott Road) – Set parapet coping
Night Work
- Pave interim WB 25 on ramp
- Median work and paving from WB 25 on ramp to former WB 24 off ramp vicinity
- Barrier moves
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.