Construction Weekly Project Update 6/05/2017
- Bridges
- Retaining Walls
- I-84 WB
- Local Roads
- Night Work
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour abutment 2 footing
- Form and pour pier 1 stem
Bridge 6590 (EB 23 on ramp)
- Pour and form abutment 1 stems and wingwall footing
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Prep for and receive structural steel delivery
- Backfill and grade west approach to bridge
Bridge 1226 (Harpers Ferry Road Bridge)
- Form and pour abutment 2 backwalls
- Bolt up structural steel members
Bridge 6284 (future EB 25 off ramp)
- Rebar deck
- Backfill abutment 2
- Set deck paving machine and run test
Retaining Walls
Retaining Wall 102 and 103 (along both sides of EB 23 on ramp)
- Backfill and set precast wall panels
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation
I-84 WB
- Install sound barrier wall east of new WB 25 off ramp
Local Roads
Reidville Drive
- Culvert 003 (east of rock cut; under Reidville Drive) – Backfill
- Culvert 1227 (east of rock cut and under I-84) – Excavate and prepare subgrade
Plank Road East
- Culvert 06622 (West of Scott Road) – Set modular wingwall
- Culvert 02537 (Beaver Pond Brook under I-84, south of WB 25 on ramp) – Backfill, set parapet, and set barrier from culvert, eastward along Retaining Wall 108
Scott Road
- Install water main (see Night Work below)
Night Work
- Barrier moves
- Scott Road water main installation: Beginning on Tuesday night, June 6 from 10:00 PM until Wednesday morning, June 7 approximately 4:00 AM, the water main at the intersection of Scott Road and Reidville Drive, and neighboring area, will be shut down to allow for the new water main, over the new Scott Road Bridge, to be connected with the old water main. If inclement weather causes postponement, work will be performed the following day.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.