Construction Weekly Project Update 5/29/2017
- Bridges
- Retaining Walls
- I-84 WB
- Local Roads
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and pour abutment 1 footing
- Excavate abutment 2 footing
Bridge 6590 (EB 23 on ramp)
- Pour and form abutment 1 stems and wingwall footing
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour abutment 2 backwalls
- Prep for and receive structural steel delivery
- Backfill and remove cofferdam abutment 2
- Remove asphalt and concrete base on former EB approaches to bridge
Bridge 1226 (Harpers Ferry Road Bridge)
- Form and pour abutment 2 backwalls
- Bolt up structural steel members
Bridge 6284 (future EB 25 off ramp)
Retaining Walls
Retaining Wall 102 and 103 (along both sides of EB 23 on ramp)
- Backfill and set precast wall panels
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation
I-84 WB
- Install sound barrier wall east of new WB 25 off ramp
Local Roads
Reidville Drive
- Culvert 003 (east of rock cut; under Reidville Drive) – Backfill
Plank Road East
- Culvert 06622 (West of Scott Road) – Set modular wingwall
- Culvert 02537 (Beaver Pond Brook under I-84, south of WB 25 on ramp) – Backfill, set parapet, and set barrier from culvert, eastward along Retaining Wall 108
Scott Road
- Install water mains and drainage (night)
Night Work
- Scott Road: utilities installation and barrier moves
Rock Blasting
Rock blasting to occur at Hamilton Avenue abutment 2 vicinity:
- When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.
Traffic stoppages on local roads including Hamilton Avenue to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.