Construction Weekly Project Update 5/08/2017
- Bridges
- Retaining Walls
- I-84
- Local Roads
- Night Work
- Rock Blasting
- Waste Stockpile Area (WSA)
Bridges
Bridge 4321 (Hamilton Avenue over I-84)
- Form and rebar pier 1 footing
Bridge 6590 (EB 23 on ramp)
- Pour and form pier stem
- Install drainage structures and pipes
Bridge 1224 (I-84 bridge over Mad River, western crossing)
- Form and pour abutment 1 backwalls and pedestals
- Form and pour abutment 2 stem
Bridge 1226 (Harpers Ferry Road Bridge)
- Survey and bolt up structural steel
- Install utility hangers/conduits/gas
Bridge 5774 (future I-84 bridge over Mad River)
- Pour concrete for EB deck
- Rebar WB deck
- Set Gomaco deck machine and test run WB deck
Bridge 6284 (future EB 25 off ramp)
Bridge 1228 (Scott Road Bridge)
- Steel delivery (steel to be stored on future WB 25 off ramp)
Retaining Walls
Retaining Wall 101 (along WB I-84 and east of WB 23 off ramp)
Retaining Wall 106 (north of WB I-84 west of WB 25 off ramp)
- Continue soil nail and excavation
I-84
- EB: New EB 25 off ramp – cut and fill roadway section, and install drainage
- EB: Rock blasting east of EB 23 on ramp to Austin Road
- WB: Install sound barrier wall along new WB 25 off ramp
Local Roads
Reidville Drive
- Install utility poles
- Form and pour cut-off and culvert pours for Culvert 003 (east of rock cut; under Reidville Drive)
Plank Road (Cul-de-sac to Harpers Ferry Road)
- Place curb, sidewalk, and subbase
Plank Road East
- Culvert 06622 (West of Scott Road) Set modular wingwall
- Culvert 02537 (Beaver Pond Brook under I-84, south of WB 25 on ramp) construct wing walls
Night Work
- Miscellaneous pothole repair and drainage
Rock Blasting
Rock blasting to occur on the East End of Project:
- East of EB 23 on ramp to Austin Road
- When I-84 needs to be stopped for safety reasons, blasting will occur on Tuesday, Wednesday, and Thursday between 9:30 AM and 11:30 AM. When no traffic stoppage on I-84 is required blasting may occur Monday through Friday from 9:00am – 3:00pm.
Traffic stoppages on local roads including Scott Road and Reidville Drive to be implemented at time of blasts for safety reasons.
Waste Stockpile Area (WSA)/Temporary Reuse Stockpile Area (TRSA)
Trucking of controlled materials from WSA on Route 322 at Exit 28 to disposal facility (ongoing); Trucking excavated material to TRSA at Exit 30 WB.